Filters
Question type

Study Flashcards

A project requires an initial investment of $10,000, straight-line depreciable to zero over four years. The discount rate is 10%. Your tax bracket is 34% and you receive a tax credit for negative earnings in the year in which the loss occurs. Additional information for variables with forecast error are shown below. A project requires an initial investment of $10,000, straight-line depreciable to zero over four years. The discount rate is 10%. Your tax bracket is 34% and you receive a tax credit for negative earnings in the year in which the loss occurs. Additional information for variables with forecast error are shown below.   Suppose you want to conduct a sensitivity analysis for the possible changes in unit sales. What is the IRR when the sales level equals 3,250 units? A)  32.6% B)  42.8% C)  57.9% D)  118.6% E)  121.5% Suppose you want to conduct a sensitivity analysis for the possible changes in unit sales. What is the IRR when the sales level equals 3,250 units?


A) 32.6%
B) 42.8%
C) 57.9%
D) 118.6%
E) 121.5%

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

The percentage change in firm (or project) operating cash flow relative to the percentage change in quantity sold is called (the) :


A) Cash flow marginal profit.
B) Degree of operating leverage.
C) Gross profit.
D) Net profit.
E) Financial break-even.

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

Which one of the following statements concerning sensitivity analysis is correct?


A) A project that has positive internal rates of return under the base, best, and worst case scenarios is a project that will produce a positive net present value under all three of those conditions.
B) When measuring the sensitivity of the sales price, the estimated variable cost per unit used in the analysis should be changed in direct proportion to the change in the estimated level of sales.
C) The most common approach to sensitivity analysis is to simultaneously vary sales in an upward direction as the estimated costs are varied in a downward direction to estimate the most optimistic outcome that can be reasonably expected.
D) Sensitivity analysis on the sales quantity generally indicates that the net present value of a project is inversely related to the quantity of units produced and sold.
E) The amount of forecast risk in any one variable can be ascertained using sensitivity analysis.

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

The analysis of the effects on a project's net present value when only one variable changes is called ______ analysis.


A) Simulation.
B) Upper and lower bound.
C) Scenario.
D) Sensitivity.
E) Break-even.

F) All of the above
G) C) and E)

Correct Answer

verifed

verified

Taking into account the managerial options implicit in a project is called:


A) Managerial oversight.
B) Tactical planning.
C) Strategic planning.
D) Contingency planning.
E) Constrained capital budgeting analysis.

F) All of the above
G) B) and D)

Correct Answer

verifed

verified

What is the degree of operating leverage? Sales = 100,000 units; price = $50; variable cost = $30; fixed costs = $950,000; depreciation = $250,000; tax rate = 34%.


A) 1.06
B) 1.22
C) 1.37
D) 1.63
E) 2.22

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

If you see a worst-case scenario for a project, the analyst is likely using ______________.


A) Scenario analysis.
B) Sensitivity analysis.
C) Base-case analysis.
D) Simulation analysis.
E) Multiple-outcome analysis.

F) B) and C)
G) D) and E)

Correct Answer

verifed

verified

The higher the degree of operating leverage, the lower the break-even point, regardless of how it's measured.

A) True
B) False

Correct Answer

verifed

verified

Provide a definition for the term simulation analysis.

Correct Answer

verifed

verified

A combination of sce...

View Answer

Which one of the following statements related to variable costs is correct?


A) Variable costs fluctuate over the long-term but remain constant over the short-term.
B) An increase in the variable cost per unit increases the contribution margin.
C) Variable costs change only when the quantity is varied by at least five percent.
D) When production is halted, the variable costs of a project equal zero.
E) The variable cost per unit is equal to the marginal cost at any level of output.

F) D) and E)
G) A) and E)

Correct Answer

verifed

verified

The possibility that errors in projected cash flows can lead to incorrect estimates of net present value is called _____ risk.


A) Forecasting.
B) Projection.
C) Scenario.
D) Monte Carlo.
E) Accounting.

F) A) and B)
G) A) and E)

Correct Answer

verifed

verified

Capital intensive projects have a high degree of operating leverage.

A) True
B) False

Correct Answer

verifed

verified

A project has earnings before interest and taxes of $5,750, fixed costs of $50,000, a selling price of $13 a unit, and a sales quantity of 11,500 units. Depreciation is $7,500. What is the variable cost per unit?


A) $6.75
B) $7.00
C) $7.25
D) $7.50
E) $7.75

F) C) and D)
G) B) and E)

Correct Answer

verifed

verified

Which of the following best describe the term forecasting risk.


A) The percentage change in operating cash flow relative to the percentage change in quantity sold.
B) The sales level that results in a zero NPV.
C) Costs that do not change when the quantity of output changes during a particular time period.
D) The possibility that errors in projected cash flows lead to incorrect decisions.
E) Opportunities that managers can exploit if certain things happen in the future.

F) A) and D)
G) B) and D)

Correct Answer

verifed

verified

Which of the following does NOT correctly complete this sentence: A project that just breaks even in an accounting sense ___________________.


A) Will lose money in a financial sense.
B) Will result in zero taxes paid.
C) Will not contribute to net income for the firm.
D) Will have a payback period less than the life of the project.
E) Will have operating cash flow equal to depreciation expense.

F) C) and D)
G) None of the above

Correct Answer

verifed

verified

The Wiltmore Co. would like to add a new product to complete their lineup. They want to know how many units they must sell to limit their potential loss to their initial investment. What is this quantity if their fixed costs are $12,000, the depreciation expense is $2,500, and the contribution margin is $1.30? (Round to whole units)


A) 9,231 units
B) 9,903 units
C) 10,002 units
D) 10,629 units
E) 11,154 units

F) C) and E)
G) A) and B)

Correct Answer

verifed

verified

Which of the following statements regarding operating leverage is correct?


A) All else the same, firms with high operating leverage have higher total fixed costs.
B) It is generally easier to decrease operating leverage than it is to increase it.
C) All else the same, operating leverage will rise as output increases.
D) In order to calculate the degree of operating leverage all that is needed are variable costs and operating cash flows.
E) All else the same, the degree of operating leverage rises as the price per unit is increased.

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

A golf course/property developer buys twice as much land as is needed to build an 18 hole golf course and housing development so that, if things go very well, a second 18 hole golf course and housing project can be added to the project. The developer is prepared to exercise the:


A) Option to default.
B) Option to expand.
C) Option to abandon.
D) Option to wait.
E) Option to rebuild.

F) C) and E)
G) A) and E)

Correct Answer

verifed

verified

To increase the contribution margin a firm must either _____ or _____.


A) Increase its sales price; increase its fixed cost per unit.
B) Increase its sales price; decrease its variable cost per unit.
C) Increase its sales price; decrease its fixed cost per unit.
D) Increase its variable cost per unit; decrease its fixed cost per unit.
E) Decrease its variable cost per unit; decrease its fixed cost per unit.

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

The accounting break-even production quantity for a project is 6,208 units. The fixed costs are $27,400 and the contribution margin is $5.20. What is the projected depreciation expense?


A) $4,413.66
B) $4,881.60
C) $5,002.50
D) $5,087.30
E) $5,133.33

F) A) and C)
G) A) and B)

Correct Answer

verifed

verified

Showing 101 - 120 of 425

Related Exams

Show Answer