Filters
Question type

Study Flashcards

The following data relate to direct labor costs for the current period:  Standard costs 36,000 hours at $23.50 Actual costs 35,000 hours at $23.00\begin{array} { l l } \text { Standard costs } & 36,000 \text { hours at } \$ 23.50 \\\text { Actual costs } & 35,000 \text { hours at } \$ 23.00\end{array} What is the direct labor time variance?


A) $23,000 unfavorable
B) $23,500 unfavorable
C) $23,500 favorable
D) $23,000 favorable

E) B) and C)
F) C) and D)

Correct Answer

verifed

verified

The standard factory overhead rate of Quaker Inc.is $10 per direct labor hour ($8 for variable factory overhead and $2 for fixed factory overhead) based on 100% capacity of 30,000 direct labor hours.The standard cost and the actual cost of factory overhead for the production of 5,000 units during May were as follows:  Standard: 25,000 hours at $10$250,000 Actual:  Variable factory overhead 202,500 Fixed factory overhead 60,000\begin{array} { l l r } \text { Standard: } & 25,000 \text { hours at } \$ 10 & \$ 250,000 \\\text { Actual: } & \text { Variable factory overhead } & 202,500 \\& \text { Fixed factory overhead } & 60,000\end{array} ? What is the amount of the fixed factory overhead volume variance?


A) $12,500 favorable
B) $10,000 unfavorable
C) $12,500 unfavorable
D) $10,000 favorable

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

The formula to compute direct materials price variance is:


A) actual costs - (actual quantity × standard price) .
B) actual cost + standard costs.
C) actual cost - standard costs.
D) (actual quantity × standard price) - standard costs.

E) B) and D)
F) A) and D)

Correct Answer

verifed

verified

The capital expenditure budget summarizes future plans for acquisition of fixed assets.

A) True
B) False

Correct Answer

verifed

verified

Standard and actual costs for direct materials for the manufacture of 2,000 units of product were as follows:  Actual costs 2,750lbs.@$8.10 Standard costs 2,800lbs.@$8.00\begin{array} { l l } \text { Actual costs } & 2,750 \mathrm { lbs } . @ \$ 8.10 \\\text { Standard costs } & 2,800 \mathrm { lbs } . @ \$ 8.00\end{array} ? Determine the (a) quantity variance, (b) price variance, and (c) total direct materials cost variance.

Correct Answer

verifed

verified

None...

View Answer

Favorable volume variances may be harmful when:


A) machine repairs cause work stoppages.
B) supervisors fail to maintain an even flow of work.
C) production in excess of normal capacity cannot be sold.
D) there are insufficient sales orders to keep the factory operating at normal capacity.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The budget procedure that requires all levels of management to start from zero in estimating sales, production, and other operating data is called zero-based budgeting.

A) True
B) False

Correct Answer

verifed

verified

If the standard to produce a given amount of product is 1,000 units of direct materials at $11 and the actual was 800 units at $12, the direct materials quantity variance was $2,200 favorable.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is true of a capital expenditures budget?


A) It summarizes plans for acquiring fixed assets.
B) It indicates all the estimated cash receipts and cash payments for a period of time.
C) It records all short-term expenses for a period.
D) It lists all the transactions related to capital stock.

E) A) and C)
F) B) and C)

Correct Answer

verifed

verified

Standards are designed to evaluate price and quantity variances separately.

A) True
B) False

Correct Answer

verifed

verified

Since the controllable variance measures the efficiency of using variable overhead resources, if budgeted variable overhead exceeds actual results, the variance is favorable.

A) True
B) False

Correct Answer

verifed

verified

The most effective means of presenting standard factory overhead cost variance data is through a factory overhead cost variance report.

A) True
B) False

Correct Answer

verifed

verified

The cash budget summarizes future plans for acquisition of fixed assets.

A) True
B) False

Correct Answer

verifed

verified

The following data relate to direct labor costs for the current period of Executive Inc.:  Standard costs 6,000 hours at $12.00 Actual costs 7,500 hours at $11.60\begin{array} { l l } \text { Standard costs } & 6,000 \text { hours at } \$ 12.00 \\\text { Actual costs } & 7,500 \text { hours at } \$ 11.60\end{array} ? What is the direct labor time variance?


A) $17,400 favorable
B) $17,400 unfavorable
C) $18,000 favorable
D) $18,000 unfavorable

E) A) and C)
F) None of the above

Correct Answer

verifed

verified

Budgetary slack can be avoided if lower and mid-level managers are requested to support all of their spending requirements with specific operational plans.

A) True
B) False

Correct Answer

verifed

verified

The standard fixed factory overhead rate is based on 100% capacity of 135,000 machine hours for Interile Inc.The standard costs and the actual costs of factory overhead for the production of 32,000 units during March were as follows:  Actual: Factory overhead $860,000 Standard: 100,000 hours at $8.00800,000\begin{array} { l r } \text { Actual: Factory overhead } & \$ 860,000 \\\text { Standard: } 100,000 \text { hours at } \$ 8.00 & 800,000\end{array} ? If there was a $70,000 unfavorable volume variance for March, what is the standard fixed factory overhead cost rate?


A) $2.00
B) $2.50
C) $3.00
D) $3.50

E) A) and D)
F) C) and D)

Correct Answer

verifed

verified

Based on the following information, calculate the direct materials quantity variance.  Actual quantity 2,500 pounds at $6.00 Standard quantity 2,900 pounds at $5.50\begin{array} { l l } \text { Actual quantity } & 2,500 \text { pounds at } \$ 6.00 \\\text { Standard quantity } & 2,900 \text { pounds at } \$ 5.50\end{array} ?


A) $2,250 unfavorable
B) $2,200 favorable
C) $2,500 favorable
D) $2,700 unfavorable

E) All of the above
F) A) and D)

Correct Answer

verifed

verified

If Division Inc.expects to sell 200,000 units in 2016, desires ending inventory of 24,000 units, and has 22,000 units on hand as of the beginning of the year, the budgeted volume of production for 2016 is 198,000 units.

A) True
B) False

Correct Answer

verifed

verified

When budget goals are set too tight, the budget becomes less effective for planning and controlling operations.

A) True
B) False

Correct Answer

verifed

verified

The difference between the budgeted fixed overhead at 100% of normal capacity and the standard fixed cost for the actual units produced is termed volume variance.

A) True
B) False

Correct Answer

verifed

verified

Showing 21 - 40 of 178

Related Exams

Show Answer