Filters
Question type

Study Flashcards

Which one of the following characteristics best describes a project that has a low degree of operating leverage?


A) high variable costs relative to the fixed costs
B) relatively high initial cash outlay
C) an OCF that is highly sensitive to the sales quantity
D) high level of forecasting risk
E) a high depreciation expense

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

Which one of the following represents the level of output where a project produces a rate of return just equal to its requirement?


A) capital break-even
B) cash break-even
C) accounting break-even
D) financial break-even
E) internal break-even

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

As the degree of sensitivity of a project to a single variable rises, the:


A) less important the variable to the final outcome of the project.
B) less volatile the project's net present value to that variable.
C) greater the importance of accurately predicting the value of that variable.
D) greater the sensitivity of the project to the other variable inputs.
E) less volatile the project's outcome.

F) B) and C)
G) D) and E)

Correct Answer

verifed

verified

Given the following, which feature identifies the most desirable level of output for a project?


A) operating cash flow equal to the depreciation expense
B) payback period equal to the project's life
C) discounted payback period equal to the project's life
D) zero IRR
E) zero operating cash flow

F) A) and D)
G) C) and D)

Correct Answer

verifed

verified

The procedure of allocating a fixed amount of funds for capital spending to each business unit is called:


A) marginal spending.
B) capital preservation.
C) soft rationing.
D) hard rationing.
E) marginal rationing.

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

At a production level of 4,500 units, a project has total costs of $107,000.The variable cost per unit is $12.50.Assume the firm can increase production by 1,000 units without increasing its fixed costs.What will the total costs be if 4,800 units are produced?


A) $102,780
B) $104,640
C) $106,400
D) $108,000
E) $110,750

F) B) and E)
G) A) and D)

Correct Answer

verifed

verified

Mr.Bear, your boss, will only agree to accept a project that, as a minimum, provides a rate of return equal to the requirement he has set for the project.Given this, explain how you can use break-even analysis to ascertain which projects will be acceptable to him as you don't want to risk hearing him growl if you waste his time presenting him with a project that is unacceptable.

Correct Answer

verifed

verified

The financial break-even quantity is the...

View Answer

Variable costs can be defined as the costs that:


A) remain constant for all time periods.
B) remain constant over the short run.
C) vary directly with sales.
D) are classified as non-cash expenses.
E) are inversely related to the number of units sold.

F) All of the above
G) B) and D)

Correct Answer

verifed

verified

The CFO of Edward's Food Distributors is continually receiving capital funding requests from its division managers.These requests are seeking funding for positive net present value projects.The CFO continues to deny all funding requests due to the financial situation of the company.Apparently, the company is:


A) operating at the accounting break-even point.
B) operating at the financial break-even point.
C) facing hard rationing.
D) operating with zero leverage.
E) operating at maximum capacity.

F) A) and E)
G) B) and D)

Correct Answer

verifed

verified

A project has the following estimated data: price = $74 per unit; variable costs = $39.22 per unit; fixed costs = $6,500; required return = 8 percent; initial investment = $8,000; life = 4 years.Ignore the effect of taxes.What is the degree of operating leverage at the financial break-even level of output?


A) 2.716
B) 3.691
C) 4.528
D) 6.003
E) 7.337

F) A) and C)
G) C) and E)

Correct Answer

verifed

verified

A proposed project has fixed costs of $36,000 per year.The operating cash flow at 18,000 units is $58,000.What will be the new degree of operating leverage if the number of units sold rises to 18,500?


A) 1.46
B) 1.59
C) 1.67
D) 2.08
E) 2.14

F) A) and B)
G) All of the above

Correct Answer

verifed

verified

Spencer Tools would like to offer a special product to its best customers.However, the firm wants to limit its maximum potential loss on this product to the firm's initial investment in the project.The fixed costs are estimated at $21,000, the depreciation expense is $11,000, and the contribution margin per unit is $12.50.What is the minimum number of units the firm should pre-sell to ensure its potential loss does not exceed the desired level?


A) 1,220 units
B) 1,680 units
C) 2,215 units
D) 2,560 units
E) 2,750 units

F) B) and C)
G) All of the above

Correct Answer

verifed

verified

Steele Insulators is analyzing a new type of insulation for interior walls.Management has compiled the following information to determine whether or not this new insulation should be manufactured.The insulation project has an initial fixed asset requirement of $1.3 million, which would be depreciated straight-line to zero over the 12-year life of the project.Projected fixed costs are $769,000 and the anticipated annual operating cash flow is $241,000.What is the degree of operating leverage for this project?


A) 3.78
B) 3.92
C) 4.19
D) 4.27
E) 4.53

F) C) and D)
G) C) and E)

Correct Answer

verifed

verified

Sunset United is analyzing a proposed project.The company expects to sell 15,000 units, plus or minus 4 percent.The expected variable cost per unit is $120 and the expected fixed costs are $311,000.The fixed and variable cost estimates are considered accurate within a plus or minus 3 percent range.The depreciation expense is $74,000.The tax rate is 35 percent.The sales price is estimated at $170 a unit, plus or minus 2 percent.What is the contribution margin per unit for a sensitivity analysis using a variable cost per unit of $125?


A) $30
B) $45
C) $50
D) $24
E) $27

F) C) and E)
G) None of the above

Correct Answer

verifed

verified

Assume that a country experiences a financial crisis that causes the nation's financial markets to freeze in a manner that prevents a private firm from raising capital from any source.Explain how project analysis conducted by that firm would work in this situation.

Correct Answer

verifed

verified

This situation is known as hard rationin...

View Answer

Stellar Plastics is analyzing a proposed project.The company expects to sell 12,000 units, plus or minus 5 percent.The expected variable cost per unit is $3.20 and the expected fixed costs are $30,000.The fixed and variable cost estimates are considered accurate within a plus or minus 5 percent range.The depreciation expense is $24,000.The tax rate is 34 percent.The sales price is estimated at $7.50 a unit, plus or minus 4 percent.What is the operating cash flow for a sensitivity analysis using total fixed costs of $31,000?


A) $19,580
B) $21,756
C) $27,210
D) $31,460
E) $37,540

F) C) and E)
G) A) and B)

Correct Answer

verifed

verified

The contribution margin per unit is equal to the:


A) sales price per unit minus the total costs per unit.
B) variable cost per unit minus the fixed cost per unit.
C) sales price per unit minus the variable cost per unit.
D) pre-tax profit per unit.
E) aftertax profit per unit.

F) C) and E)
G) B) and C)

Correct Answer

verifed

verified

When the operating cash flow of a project is equal to zero, the project is operating at the:


A) maximum possible level of production.
B) minimum possible level of production.
C) financial break-even point.
D) accounting break-even point.
E) cash break-even point.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Which one of the following will be used in the computation of the best-case analysis of a proposed project?


A) minimal number of units that are expected to be produced and sold
B) the lowest expected salvage value that can be obtained for a project's fixed assets
C) the most anticipated sales price per unit
D) the lowest variable cost per unit that can reasonably be expected
E) the highest level of fixed costs that is actually anticipated

F) A) and C)
G) A) and E)

Correct Answer

verifed

verified

Which of the following variables will be at their highest expected level under a worst case scenario? I.fixed cost II.sales price III.variable cost IV.sales quantity


A) I only
B) III only
C) II and III only
D) I and III only
E) I, III, and IV only

F) A) and B)
G) A) and E)

Correct Answer

verifed

verified

Showing 41 - 60 of 105

Related Exams

Show Answer